Smiltene Wind Farm – Construction Progress Update

All foundation concrete works have been completed. Electrical installation and cable installation works are ongoing.

All access roads and hardstanding areas, including road upgrades required for turbine deliveries, have been completed.

The installation of four wind turbines has been fully completed, and more than half of all turbine components have been delivered to the site.