Smiltene Wind Farm – Construction Progress Update
In the final phase of the turbine foundation piling works, 14 out of 16 have been fully completed. Three of the 16 foundations have been concreted. All foundation concreting works are planned to be completed in April–May.
The redesign of access roads P29, V235, and V267 to ensure turbine deliveries is ongoing.
The approval process for the mobile concrete plant with the state authorities is ongoing.