Start of the civil works

Smiltene wind farm construction works are now about to start with the civil works phase which will include deforestation, road construction, cabling and wind turbine foundation construction.

Site compound and storage area have been prepared and next the deforestation and road construction will take place.

Actual civil works (road construction, etc) will start from areas indicated on the map from CW35.

Preparatory works (deforestation, tree stamp removal, etc) have started in CW34.

Start of the cabling works and foundation construction will be informed separately.

In addition to the works on site are deliveries of cables, materials for foundations and aggregates will start increasing traffic in the area.

Substation works has been started and is ongoing with civil and foundation works as well as the construction of the substation building.